A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Time Most Likely Time Pessimistic Time A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 E B 4 6 11 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 I G 2 4 6 J H 4 7 9 K I, J 4 7 8 a) Calculate the expected duration (D), and variance of each activity. b) Calculate ES, EF, LS, LF, S for each activity.
Added by Rosario G.
Close
Step 1
0 weeks, Variance = (14 - 4) / 6 = 1.67 - For Activity B: D = (4 + 0 + 10) / 6 = 2.33 weeks, Variance = (10 - 4) / 6 = 1.0 - For Activity C: D = (0 + 0 + 10) / 6 = 1.67 weeks, Variance = (10 - 0) / 6 = 1.67 - For Activity D: D = (4 + 5 + 14) / 6 = 4.5 weeks, Show more…
Show all steps
Your feedback will help us improve your experience
Shyam P and 95 other Calculus 3 educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
Question 3: (a) Explain the following terms in PERT: i. Optimistic time ii. Normal time iii. Pessimistic time iv. Expected time v. Variance in relation to activities. (b) A project schedule has the following characteristics: Activity Time (weeks) Activity Time (weeks) 1-2 4 5-6 4 1-3 1 5-7 8 2-4 1 6-8 1 3-4 1 7-8 2 3-5 6 8-10 5 4-9 5 9-10 7 i. Construct the network ii. Compute the earliest time (E) and latest time (L) iii. Find the critical path
Sri K.
Madhur L.
Time of Traffic Fatality In Exercise 51 of the previous section, the probability density function for the number of fatal traffic accidents was found to be $$S(t)=\frac{1}{91,762}\left(-2.416 t^{3}+90.91 t^{2}-846.8 t+4880\right)$$ where $t$ is the number of hours since midnight on $[0,24]$. Calculate the expected time of day at which a fatal accident will occur. Source: The National Highway Traffic Safety Administration.
Probability and Calculus
Expected Value and Variance of Continuous Random Variables
Recommended Textbooks
Calculus: Early Transcendentals
Thomas Calculus
Transcript
18,000,000+
Students on Numerade
Trusted by students at 8,000+ universities
Watch the video solution with this free unlock.
EMAIL
PASSWORD