Please help find the slack time for a, b, c, d, e, f, g.
The activities, immediate predecessors, and times appear in the accompanying table "Activity. Immediate Predecessor(s) Time (days)".
Program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table "Activity. Immediate Predecessor(s) Time (days)".
D
B AD C EF
1 10 4 6 10
G
This exercise can only parts B and D. The critical activities for the leadership training program development project are B-DE. The project length for the leadership training program development project is 29 days. Slack time for each of the activities is:
Activity Slack Time A