1.For the following table of information: a)Draw the network diagram(Activity on Arrow) b)List the network paths c) Determine the critical path(s
4+1+2=7 Marks
Activity Predecessor Duration A Start 5 days B Start 2days C B 3days D A 5days E D 6days F C 4 days G E,F 2days H G 5days
2.Describe in detail about the basic tools and techniques used for Cost Estimation. (3 Marks)
(Chapter5:Project Scope,Time &Cost Management