00:01
The question is in part at part a we need to create a ga and double t chart for the project.
00:08
So how we can calculate this is activity.
00:10
This is time in week.
00:13
This is start and finish.
00:17
So first is collect requirements.
00:22
This is five zero five analyze processes.
00:29
Four five nine analyze data four five nine designing process.
00:48
Eight nine seventeen designing data five nine and fourteen design screen design screen for 1418 designing report six fourteen twenty program 718 25 test and document 920 29 install 425 9.
01:33
So this is the chart for part a now, let's move towards the part b of the question.
01:39
So in part b, we need to we need to create a network diagram.
01:49
Network diagram for activities.
01:52
So here it is one.
01:54
This is two four six eight ten.
02:01
This is basically nine...