Assume that your capstone project is broken down into a number of major jobs or activities, as shown in Table below:
Activity Description | Activity Identification | Immediate Predecessor Activity | Activity Duration (Days)
Proposal defense | A | - | 5
Problem Statement | B | - | 4
Objectives | C | A | 3
Literature review | D | A | 4
Methodology | E | A | 6
Results | F | B, C | 4
Discussion and analysis | G | D | 5
Recommendation | H | D, E | 6
Challenges | I | F | 6
Conclusion | J | G, H | 4
a. Draw a Gantt chart.
b. Develop a CPM network.
c. Determine both the critical path of the network and the project duration period