00:01
Hello students, here is a question.
00:02
Use the following project cash flow to answer the question.
00:05
So, your cash flow is $675 ,000 for the 0 years.
00:09
For the first it is $115 ,000.
00:11
For second it is $220 ,000.
00:13
For third it is $345 ,000.
00:15
Fourth is $410 ,000.
00:17
Assuming the required return of 9 % where npv of a project.
00:21
What is the npv of a project? so, we need to find the npv and irr for the project by given information in the question.
00:29
So, let us discuss the answer for this.
00:32
To calculate the npv of a project we need a discounted each cash flow for the present value of sum of the financial calculator.
00:40
So, that will be npv is equal to minus $675 ,000 plus $115 ,000 divided by 1 plus 0 .09 to the power 1 plus $220 ,000 divided by 1 plus 0 .09 to the power 2 plus $345 ,000 divided by 1 plus 0 .09 to the power 3 plus $410 ,000 divided by 1 plus 0 .09 to the power 4 where the npv will be $154 ,862 .28.
01:35
Therefore, the answer is option c.
01:40
Option c is the right answer for this question that is $154 ,862 .28...