Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for each activity, and highlight the critical path indicating the length of this project. Activity Duration (Days) Immediate Predecessor Activities A 2 - B 3 - C 4 A D 5 A & B E 8 C & D F 3 D G 2 F H 3 G
Added by Jennifer B.
Close
Step 1
- Activity A: Duration 2 days, no predecessors. - Activity B: Duration 3 days, no predecessors. - Activity C: Duration 4 days, predecessor A. - Activity D: Duration 5 days, predecessors A and B. - Activity E: Duration 8 days, predecessors C and D. - Activity F: Show moreā¦
Show all steps
Your feedback will help us improve your experience
Akash M and 77 other AP CS educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
Construct network diagram using AOA technique, estimate ES, EF, LS, and slack time of each activity. Find the Critical path and its duration. Construct Gantt chart and calculate utilization factor. Staff required is A-5, B-3, C-8, D-2, E-6, F-3. Activity | Immediate Predecessors | Duration (weeks) A | - | 2 B | A | 4 C | B | 3 D | B | 2 E | C, D | 10 F | B | 4
Adi S.
A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Duration A -- 8 B -- 3 C A 7 D A, B 3 E C 6 F D 8 Required: a. Draw the network diagram. (5 marks) b. Calculate the ES, EF, LS, LF, and Slack for each activity. (12 marks) c. What is project completion time? (3 marks)
Maitreya E.
Sri K.
Recommended Textbooks
Computer Science and Information Technology
Introduction to Programming Using Python
Computer Science - An Overview
Transcript
Watch the video solution with this free unlock.
EMAIL
PASSWORD