Compute the MIRR statistic for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project I Time:01234Cash flow:−$11,300$5,480$4,330$1,670$2,150
Should the project be accepted or rejected?
multiple choice
accepted
rejected