Activity
Description
Immediate
Time
Predecessor (weeks)
A
Survey building site
5
B
Develop initial design
8
C
Obtain board approval
A, B
11
D
Select architect
C
4
E
Establish budget
C
6
F
Finalize design
D, E
15
G
Obtain financing
E
13
H
Hire contractor
F, G
7
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
This answer has not been graded yet.
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
B,C,E,F,H
(c) Develop the activity schedule for the project.
Activity
Earliest
Start
Latest
Start
Earliest
Finish
Latest
Finish
Slack
A
B