Texts: Description
Immediate Predecessor
Time (weeks)
Activity
A
Survey building site
5
B
Develop initial design
8
C
Obtain board approval
A,B
11
D
Select architect
C
4
E
Establish budget
C
6
F
Finalize design
D,E
15
G
Obtain financing
E
13
H
Hire contractor
F,G
7
(a) Draw a project network. Submit a file with a maximum size of 1 MB. (Answer not provided)
(b) Identify the critical path. (Enter your answers as a comma-separated list.) B,C,E,F,H
(c) Develop the activity schedule for the project.
Earliest Start
Latest Start
Earliest Finish
Activity
Latest Finish
Slack
A
0
0
5
5
0
B
0
0
8
8
0
C
5
5
16
16
0
D
16
16
20
20
0
E
16
16
22
22
0
F
20
20
35
35
0
G
22
22
35
35
0
H
35
35
42
42
0