ABC Company reports the following information for the most recent period when 2,750 units were produced.
Cost Standard Actual
Materials 2 lbs. @ $5.00 per pound 7,000 pounds purchased for $34,650
Labor 0.50 hours @ $8.00 per hour 1,400 hours @ $7.95 per hour
Refer to ABC Company. Calculate the direct materials price variance.
1. $350 U
2. $7,150 U
3. $-0-
4. $350 F