Current Attempt in Progress
Aikman Corporation has the following cost records for June 2022:
Indirect factory labour $4,600 Factory utilities $600
Direct materials used 26,000 Depreciation, factory equipment 1,400
Work in process (6/1/22) 3,400 Direct labour 30,000
Work in process (6/30/22) 3,000 Maintenance, factory equipment 2,000
Finished goods (6/1/22) 5,300 Indirect materials 2,300
Finished goods (6/30/22) 9,000 Factory manager's salary 3,350