00:01
So firstly we have to see linear regression approach.
00:13
So in a tabular form, the values are given to us as month, then we have machine hours and then we have overhead cost.
00:35
So for the first month, 2500 hours and cost is 55 ,400.
00:43
For second month, 2560 hours and 57 ,620 overhead cost.
00:54
For the third month, we have 2800 machine hours and 63 ,800 overhead cost.
01:04
For the fourth month, machine hours is 3520 and overhead cost is 69 ,320.
01:13
For the fifth month, machine hours is 3 ,700 and overhead cost is 71 ,460.
01:24
For the sixth month, machine hours we have is 4 ,300 and overhead cost we have is 72 ,480.
01:36
For the seventh month, machine hours is 4 ,900 and overhead cost is 79 ,620.
01:45
For the eighth month, machine hours we have is 5 ,500 and overhead cost is 80 ,450...