On January 1, 2024, a company began construction of a new warehouse. The building was finished and ready for use on September 30, 2025. Expenditures on the project were as follows:
January 1, 2024
September 1, 2024
December 31, 2024
March 31, 2025
September 30, 2025
$340,000
$510,000
$510,000
$510,000
$340,000
The company had $7,000,000 in 14% bonds outstanding through both years.
Capitalized interest in 2024 was:
Multiple Choice
$47,600.
$83,300.
$95,200.
$71,400.