One of the choices below refers to major unforeseen risks and endeavors to supply funds for the same. Which choice is it?
A) Project reserves
B) Management reserves
C) Time buffers
D) Activity reserves
E) Contingency reserves
10)
Including the change control system within the ________ is a key to a
successful project.
A) work breakdown structure
B) project baseline
C) risk management plan
D) work breakdown structure and project baseline
E) project baseline and risk management plan
11)
According to the Failure Mode and Effects Analysis (FMEA), Impact x Probability x Detection = ________.
A) risk severity
B) risk assessment
C) risk value
D) risk mitigation
E) risk difficulty