Q6. Following are the activities of a Project, please consider them for answering the questions below: Activity Predecessor(s) Duration (days) A - 4 B - 5 C A 5 D B 6 E C, D 9 F C, D 5 G E, F 2 H D 4 I G 6 J H, I 3 K J 3 a) Draw Gantt chart for the above table (4) b) Draw Labeled Network Diagram and high light critical path. (6+1) c) Calculate total duration of the project (2) d) Make a list of all Critical Activities (2) e) Make a list of all Non Critical Activities (2) f) Find Float/ Slack for Each Activity. (3)
Added by Louis S.
Close
Step 1
Step 1: List activities with durations and predecessors: A(4,-), B(5,-), C(5,A), D(6,B), E(9,C,D), F(5,C,D), G(2,E,F), H(4,D), I(6,G), J(3,H,I), K(3,J). Show more…
Show all steps
Your feedback will help us improve your experience
Adi S and 89 other Principles of Accounting educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Recommended Videos
Assume that your capstone project is broken down into a number of major jobs or activities, as shown in Table below: Activity Description | Activity Identification | Immediate Predecessor Activity | Activity Duration (Days) Proposal defense | A | - | 5 Problem Statement | B | - | 4 Objectives | C | A | 3 Literature review | D | A | 4 Methodology | E | A | 6 Results | F | B, C | 4 Discussion and analysis | G | D | 5 Recommendation | H | D, E | 6 Challenges | I | F | 6 Conclusion | J | G, H | 4 a. Draw a Gantt chart. b. Develop a CPM network. c. Determine both the critical path of the network and the project duration period
Sri K.
Aarya B.
Consider the following information about a small project: Task Duration Estimates Immediate Predecessors A 4 days None B 6 days A C 2 days B D 3 days A E 5 days B & D F 13 days C & E a. Draw the precedence diagram and determine the earliest start time, earliest finish time, latest start time, latest finish time and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Immediate Predecessors Earliest Start (ES) Earliest Finish (EF) Latest Start (LS) Latest Finish (LF) Slack A None B A C B D A E B, D F C, E b. Identify the critical path. A-D-E-F A-B-E-F A-B-C-F c. Which of these tasks should the project manager track most closely? A-B-E-F A-D-E-F A-B-C-F
Recommended Textbooks
Horngren’s Cost Accounting
Cost Accounting A Managerial Emphasis
Principles of Accounting Volume 1: Financial Accounting
Transcript
Watch the video solution with this free unlock.
EMAIL
PASSWORD